Most federal contractors spend months on the proposal and almost no time on the question that decides whether the contract is profitable: what happens when the work changes? It will. The agency adds a task, delays site access, revises a requirement, or hands you a drawing that turns out to be wrong. If you do the extra work and say nothing, you have just absorbed the cost.
A Request for Equitable Adjustment (REA) is the mechanism for asking the government to adjust price, schedule, or both when its actions changed the cost or time of performance. It is the first step, not the last, and how you handle it often decides whether you get paid.
What an REA Is (and Is Not)
An REA is a contractor’s request, submitted to the contracting officer, for an equitable adjustment to the contract. It is a negotiation document. It is not a formal claim under the Contract Disputes Act (CDA), it does not start the CDA clock, and it does not carry the same certification requirement. Think of it as the structured conversation that resolves most disagreements before they become disputes.
An REA is also different from a modification the government initiates. If the contracting officer issues a change under the Changes clause, the contract gives you a right to an adjustment and a deadline to assert it. An REA covers those situations and others where the government’s conduct, rather than a formal change order, caused the extra cost.
When You May Have an REA
- Constructive changes:The government, without a formal change order, requires work beyond what the contract says. A contracting officer’s representative who asks for “one more report each month” may be creating one.
- Formal changes: A modification that adds, removes, or revises scope under the Changes clause.
- Government delay or disruption: Late access, late government-furnished property, or late approvals that push your schedule and raise your costs.
- Defective government information: Specifications or drawings the government supplied that could not produce the required result.
- Differing site conditions: Conditions materially different from what the contract described, most often in construction.
- Quantity or workload changes: In some contract types, material changes from the estimates the government gave in the solicitation.
The key test is whether the government, not you, caused the added cost or time. A cost you incurred because your own estimate was low is not an REA. See our guide on price-to-win strategy for how to avoid underpricing in the first place.
Notice Comes First
Many contract clauses require you to notify the contracting officer within a set time after you learn of a change, or before you perform the changed work. Missing the notice window can weaken or forfeit your right to recover, although the government must often show it was prejudiced by late notice. Read the Changes clause and any delay or site-condition clauses in your contract and put the deadlines on a calendar the day you sign.
Practically: the moment someone asks for work that looks outside the scope, put it in writing. A short email to the contracting officer saying “We understand this is additional to the contract scope and will submit an adjustment. Please confirm direction” costs you nothing and can protect everything. Do not let the contracting officer’s representative direct changes by phone while you quietly absorb the cost. Only the contracting officer can change the contract, and that is why the written notice goes to them. Our COR guide explains the limits of that role.
What a Strong REA Contains
- Contract identification and the change: Contract number, the clause or requirement affected, and a plain statement of what the government did.
- Entitlement: Why the government is responsible, tied to specific contract language, dated communications, and facts. Entitlement comes first. If you cannot show it, the numbers do not matter.
- Quantum: The amount. Break it into direct labor, materials, subcontractors, other direct costs, indirect rates, and profit, using the same estimating structure as your original proposal so the contracting officer can compare line to line.
- Schedule impact: The days of delay and the basis for them, ideally supported by your schedule.
- Supporting documents: Timesheets, invoices, emails, meeting notes, photographs, and the modification or direction at issue.
Cost-based requests are only as credible as your cost records. If you cannot trace the added cost to the change, you will negotiate from weakness. See our guide to accounting systems for federal contractors.
The Negotiation
The contracting officer will usually ask for audit support or technical review. Expect questions on whether the work was truly additional, whether the hours were reasonable, and whether the rates match your contract. Respond quickly and keep the tone factual. A bilateral modification that resolves the REA is the outcome you want, and settling for a fair number now is often better than winning a larger number years later.
Do not stop performing while the REA is pending unless the contract allows it. Contractors generally must keep working as directed, and refusing can create a default risk that outweighs the REA.
When an REA Becomes a Claim
If negotiations fail, you can convert the dispute into a formal claim under the Contract Disputes Act. A claim is a written demand to the contracting officer for payment of a sum certain, time, or other relief, and claims above the CDA threshold must be certified. The contracting officer must issue a final decision, and you can appeal that decision to the Board of Contract Appeals or the Court of Federal Claims. Claims also have a limitations period, generally six years from when the claim accrued.
Certification is not a formality. A knowingly false certification can create fraud exposure. Have counsel review any claim before it is submitted, and check the current thresholds and deadlines in FAR Subpart 33.2 and the CDA clauses in your contract. The same advice applies to termination settlements, which have their own cost-recovery rules.
Protecting Your Position From Day One
- Track every government direction in a log: date, who gave it, what it said, and whether it changed scope.
- Set up separate charge numbers for changed work so the cost is traceable from the start.
- Send written notice before or as soon as you discover a change, to the contracting officer.
- Flow the same discipline to subcontractors, since their added costs usually depend on yours.
- Keep the working relationship professional. Most REAs are settled by people who still need to work together.
Past performance matters here too. A contractor who handles changes cleanly and does not dispute everything builds the kind of record that supports strong CPARS ratings.
Bottom Line
Federal contracts change. The firms that stay profitable are the ones that notice the change early, tell the contracting officer in writing, track the cost from the first hour, and submit a clear request with both entitlement and numbers. An REA is not a confrontation. It is the contract working the way it was designed to.